1. Case-study No. & Title:
|
w |
Social development |
|
w |
Community planning |
|
w |
Communication |
|
w |
Co-existence |
|
w |
Co-operation |
2. Author information
|
w |
Reconstruction of electric installations |
|
w |
Replacement of the old electricity transformer |
|
w |
Installing the network of electricity cables that would connect transformer with the buildings and pylon |
After the end of NATO air-campaign on the FR Yugoslavia and the withdrawal of
the Yugoslav Army from Kosovo, members of the Serbian population from Kosovo
started leaving their homes and coming to Serbia. Although the majority settled
either in Montenegro and or in the towns of Vranje, Babusnica, Prokuplje, etc
(geographically closer to Kosovo), a number arrived in Nis. They are
accommodated mainly in local hotels, while some have found shelter in the
village of Sicevo, approximately 15 km east of Nis. The location where they have
settled used to be a holiday resort but it has been out of use for a long time
and is accordingly in very bad condition. The main problem was the lack of
electric power, mostly due to the age of the electric system. Refugees could not
be expected to live in such bad conditions. The Ministry for Refugees first
raised the issue. The local government of Nis region was supposed to solve the
problem, but ultimately it was the international humanitarian organization YEN
that conducted the project. This project essentially concentrated on solving
very practical tasks and comprised the following:
|
a) |
Reconstruction of electrical installations |
|
Electric installations in the buildings where the refugees are located were in such bad conditions that the local Commissariat for Refugees at first wanted to relocate refugees to some other place. There was a proposal to clad the buildings with panels and to solve problems with heating in this way. However, after YEN’s proposal to reconstruct installations both of these earlier proposals were rejected. This part of the project was financed and conducted by ICS (Italian Consortium of Solidarity). |
|
|
b) |
Replacement of the old electricity transformer |
|
The second phase of the project comprised the replacement of the old electricity transformer. Without replacing the transformer it would be impossible for the installations to work properly. The old transformer was still working but it was in very bad condition and there was a threat that it would collapse very soon. YEN financed this part of the project on its own, but the concrete job was carried out by a local electricity enterprise called ‘Elektrodistribucija – Nis’. |
|
|
c) |
Installing the network of electricity cables that would connect the transformer with the buildings and pylons |
|
The last aspect of the project comprised installing the network of electricity cables, connecting buildings with the transformer and finally the pylon. This part of the project was financed and conducted by YEN. |
|
w |
Local Government - Local Commissariat for Refugees (for region of Nis) as representatives of local authorities |
|
w |
Government Ministry |
|
w |
Public Institution |
|
w |
International NGO – YEN, ICS (Italian Consortium of Solidarity) |
|
w |
Private institution or enterprise - "Elektrodistribucija – Nis" (local electricity company) |
|
w |
Other, namely: UNHCR |
3.5 Budget allocated by local government authorities and/or by other actors
|
Reconstruction of electric installations in the refugee camp in Sicevo: |
|
|
Humanitarian organization YEN |
|
|
Replacement of the old electricity transformer in the camp: |
|
|
Humanitarian organization YEN |
|
|
Installing the whole network of electricity transformers: |
|
|
Humanitarian organization YEN |
|
|
Total amount of money spent on the project: |
|
|
Approximately US$ 13,000, out of which 70% was spent on equipment. |
|
|
w |
The reconstruction of electric installations was the first part of the project to be carried out. This work was started in the beginning of November 2000. Electric installations in all the buildings were replaced. There was a relatively minor problem this work being carried out while the refugees were in the buildings, but this did not affect successful outcome. The humanitarian organization YEN was directly responsible for this part of the project, although the Italian Consortium of Solidarity provided financial support for it and did the practical work. |
|
w |
Replacement of the old electricity transformer was the second part of the project. This was done shortly after the reconstruction of the electric installations. This part of the project is very important because without it, it would be impossible to successfully solve the problem with electric power. The old electricity transformer was still in use but due to its instability there was a danger of its (and the whole system’s) imminent collapse. This part of project was finished in a hurry because of the weather conditions. YEN financed the replacement, but the work in the field were carried out by the local electricity enterprise, "Elektrodistribucija – Nis". |
|
w |
The last part of the project was the installation of the network of electricity cables that would connect the transformer with the buildings and pylon. This part was also very contingent upon the weather conditions, since a large part of work was to be done outside. This final part of the project was finished in the first half of January 2001. The humanitarian organization YEN as the main organizer and financier was solely responsible for this part of the project. |
A very important aspect of the project was getting in touch with the refugees.
This is the first non-practically oriented aspect and its outcomes are not that
visible. However, YEN is a humanitarian organization that not only helps with
the reconstruction of buildings and similar projects, but also organizes
workshops providing psychological help for refugees. The project to bring
electricity to the Siveco refugee camp does not encompass such workshops, but it
is important because essential connections with refugees are made. As Ms Suzuje
Saito and other representatives of YEN said, this project might have a
continuation that would consist of such workshops.